Over the next 14 months, the city will repair and resur-face Wahiawa’s long, bumpy road, California Avenue, via a $7.2 million project contracted to Road Builders Corp.

Concrete work began two weeks ago. Work hours are 8:30 am. to 3:30 p.m. week-days with periodic lane closures and delays.

Work includes demolition and removal of existing pavement, curbs and/or gutters; installation of aggregate base course, geogrid and woven geotextile, asphalt concrete base and asphalt concrete pavement; installation of grade adjustment curb; construction of new concrete slabs, curbs and gutters; tree and root trimming and pruning as needed; adjustment of street monuments and manholes; restoration of all pavement loop detectors, striping, markings and markers.

Over the next 14 months, the city will repair and resur-face Wahiawa’s long, bumpy road, California Avenue, via a $7.2 million project contracted to Road Builders Corp.


The project is expected to take up to 425 days.

For more information, call 768-8815.

E-mail this story | Print this page | Comments (0) | Archive | RSS

Most Recent Comment(s):

Posting a comment on MidWeek.com requires a free registration.

Username

Password

Auto Login

Forgot Password

Sign Up for MidWeek newsletter Times Supermarket
Foodland

 

 



Hawaii Luxury
Magazine


Tiare Asia and Alex Bing
were spotted at the Sugar Ray's Bar Lounge